George Chesser, as Electrical Superintendent, has served as a key member of the Project Management Team. In this role, he has supported the planning and production efforts of the General Foreman and Foreman to achieve the total project goals and objectives by forming an effective team and delegating responsibilities. George sets exemplary standards for corporate safety, quality and productivity by implementing and monitoring project control systems and providing on-the-job training.
EDUCATION AND SPECIAL TRAINING
OSHA Safety Courses and Chemical Effects Training Poison
Control, CPR, and Emergency Response Training
EXPERIENCE
03/06/08 to 08/01/08 - Electrical Superintendent, BE&K, New Baghouse at Plant Scherer, Jouliett, Georgia.
Completed E&I installation Grass Root Project.
10/20/06 to 11/04/07 - Electrical Superintendent, Ethanol Plant producing 44,000,000 gallons a year. Responsible for all the electrical, incoming power throughout the plant including the duct banks. Large control unit with 4160 volts/480 volts supporting the motors.
06/24/05 to 01/02/06, Electrical Superintendent, TIC Construction Company, Dell Arkansas
Work was approximately 40% completed. Straightened out electrical work and completed the job.
03/20/05 to 09/25/05 - Electrical Superintendent, Alabama Power Company, Motor Division Plant
for Honda at the Alabama Plant.
Responsible for all the building lighting, and pulling power cables to support all the electrical equipment needed to operate the motor division plant for Honda (Alabama).
08/09/04 to 02/20/05 - Superintendent, Muscogee County Correctional Center, Midland, Georgia,
ACE/Putzel Electric.
Supervised a crew of 20 men (Journeymen and Electrical Helpers) at the Muscogee County Correctional Center located in Midland, Georgia. Work completed included the installation of electrical system, security, ups, and lighting systems for facility. Construction areas included: administrative building, holding cells, doctor's suite, dental lab, processing area for new inmates, kitchen, security room, book work rooms, and all administrative offices.
10/01/03 to 05/30/04 - Electrical Superintendent, Brighton Beach Power Plant, Windsor Ontario,
Canada.
Supervised a crew of 30+ men performing startup for a power plant. Tasks included: QA's of all electrical, motors, valves, PLC and instruments. Other checks included associated interlocks and switches that related to all motors. Then all switchgear (individual voltage ranged from 13,800 to 120 volts) was checked for the 600 M.W. two (2) unit plant. Lastly, a total system check was completed and the plant was approved for operation.
GEORGE CHESSER Page 2
10/10/02 to 10/01/03 - Electrical Superintendent, Caddell, Inc., Goat Rock Power Plant, Smiths,
Alabama.
Responsible for overall electrical construction of new power plant including supervision of over 90 employees. Provided strong input on construction costs, scheduling and purchasing. Facilitated communication with all departments involved in construction activities. During the course of construction, achieved schedule, budget and administrative goals while working independently and with a team.
09/01/01 to 09/20/02 - Electrical & Instrumentation Superintendent, Goat Rock 500 MW Power Block Combined Cycle Power Plant, Smiths, Alabama, location: Southern Company Services, owner. TIC was the general contractor for work that included all above ground piping, electrical and mechanical. Major systems of work included station service, cooling tower, waste water, filtered water, makeup and blowdown, demin water, water analysis hydrogen & CO2, GTA gas system GIB gas system, condensate, A feed water, B feed water, steam piping valves and TWIP ammonia, CTG-A, CIG-B, HRSG-A, HRSG-B, and steam turbine. Major equipment installed included GE 7FA, combustion turbine, GE D 11 S steam turbine and Vogt-Nem Heat Recovery Steam Generator.
07/20/00 to 09/01/01 - Electrical Superintendent, 1040 MW Combined Cycle Project, Pascagoula,
Mississippi, location: Southern Company Services, owner and engineer.
TIC was the general contractor for the expansion of an existing coal-fired power facility by the installation of two combined cycle units each consisting of two 150 MW GE 7FA gas turbines and one 220 MW steam turbine. Scope of work includes structural, mechanical, electrical, instrumentation and commissioning.
06/15/90 to 06/12/00 - Electrical & Instrumentation Superintendent, SECO Industries, Beaumont, Texas.
Successfully managed multiple projects while supervising crew of over 110 employees.
Duties included development of bid schedules, performing quantity take-off, preparation of
bids for review and submittal, finalization of contracts and preparation of RDI's and CCO's.
Provided strong input on construction costs, estimating, scheduling and purchasing.
1990 to 1994 - Self Employed. Operated as an Electrical Contractor preparing custom built homes. Tasks included total electrical, lighting, and home security systems per city code. Other duties: purchasing materials, scheduling work, and supervising crew all within budget and schedule. Produced an average of 40 homes a year priced from $110,000 to $400.000.
References Available Upon Request
NukeJobs is a nuclear jobs board that provides nuclear job seekers access to international directories of Nuclear Employers, Nuclear Resumes and Nuclear Jobs such as Nuclear Engineer Jobs, Nuclear Construction Jobs, Nuclear Power Plant Jobs, Nuclear Medicine Jobs, Nuclear Pharmacy Jobs, Nuclear Security Jobs, Nuclear Physics Jobs, Nuclear Reactor Jobs, Nuclear Material Jobs, Nuclear Safety Jobs, and Nuclear Waste Jobs.