Robert J. Griep
217 Isabella Street
Hayward, CA 94544
(510) 538-3767
OBJECTIVE: To obtain a challenging supervisory position with an established,
high volume construction company.
EXPERIENCE: January, 2005 – To Present
BBI Construction, Inc., Oakland, CA
Assisted preconstruction efforts, plan review and schedule
Development with attention to critical path.
Developed and implemented site planning, logistics and procedures fore execution of the work.
Coordinated, directed and monitored the activities of the
subcontractors, supplies, company labor and material.
Ensured work performed complied with all requirements of the
inspection agencies.
Established and enforced a comprehensive project safety and
security program as defined by the company and OSHA.
Worked closely with the project managers, owners, architects and
City officials to accomplish completion of projects on time.
July, 2003 – October, 2004
Arntz Builders, Inc., Novato, CA
As superintendent reviewed construction documents for
discrepancies.
Implemented and updated weekly schedules.
Provided accurate and detailed daily and safety reports.
Organized labor and material to maximize efficiency.
Assumed sole responsibility of critical lay out.
Aided as necessary to meet demanding time frame.
Generated amiable relations with school officials, architects,
engineers and project managers throughout the school district.
Robert J. Griep
Page Two
March, 2002 – June, 2003
E. A. Davidovits Construction Co., Redwood City, CA
Assembled submittal packages for review and approval of
client/engineer.
Implemented stringent safety program.
Attended weekly meetings with owner’s representative.
Provided input to aggressively complete project.
Coordinate and monitor subcontractor installations and
workmanship.
Sole responsibility of layout in all phases to expedite construction.
June, 1993 – March 2002
Vitton Construction Company, San Leandro, CA
Organize and implement job set up with emphasis on accurate
daily reports and safety records.
Review plans and specification prior to construction for any
discrepancies.
Work closely with project manager to successfully complete
project on schedule, advise of conflicts promptly to avoid
problems or delays.
Develop and implement aggressive schedules. Aid in making
estimates of labor time in relation to set bid costs for future
projects.
Act as a liaison between subcontractors and architects to ensure
information is readily available.
As superintendent, laid out all critical building dimensions while
maintaining a high level of accuracy throughout the project.
Ordered all materials, obtaining bids when necessary to expedite
construction.
Evaluated, hired and instructed new employees in proper
construction techniques and safety.
Cultivated client rapport with school districts, port authority,
private owners and city officials.
Robert J. Griep
Page Three
September, 1979 – May, 1993
Barnhill Construction Co., Alameda, CA
As superintendent set up jobs and organized labor to maximize
efficiency in all phases of the project.
Schedule and oversee all subcontractors to ensure quality
performance.
Lay out and review all building dimensions.
Initiate all inspections required to keep continuity during
construction.
Acted as an emissary of owner while lending institution, salesmen
and developers were on site.
Interviewed and hired new employees. Trained with a “hands onâ€
approach to gain respect and motivation.
April, 1972 – September, 1979
Barnhill Construction Co., Alameda, CA
As Apprentice Carpenter/Carpenter Foreman, assisted in completion of 12 projects, attended college and completed
a six year reserve term in the National Guard.
Worked in difficult phases of building construction,
Supervised crews, laid out all building dimensions and examined
concrete placements.
Kept tools operable and necessary materials in constant supply.
Interacted well with owner and superintendents and implemented
Their directives to my crews.
ACCOMPLISHMENTS:
Constructed numerous, intricate projects.
Received letters of commendation from:
Joe Wong, Port of Oakland - June, 1997
Kim Fogarty, One Color Communications - January, 1995
Fred Foster, Concord City Hall – July, 1996
Certified Forklift Operator
Basic computer Skills and Prolog experience
EDUCATION:
January, 1977–Certificate of Completion in Apprentice Carpentry
June, 1973–AA Degree in Economics, ChabotCollege-Hayward
June, 1970-Graduated Bishop O’Dowd High School, Oakland
PROJECT HISTORY
John Muir Middle School & Super Taqueria
Roosevelt Grammar School San Jose, CA
San Leandro, CA 4,000 SF. $1,000,000
Multi-wing task. Abatement/seismic upgrade Ground-up wood frame structure
ADA compliance and fire safety. Completed restaurant. Turnkey occupancy.
while classes in session.
Valley Transit Authority Greenville Corporate Cntr.I&II
Parts & Storage Facility Livermore, CA
San Jose, CA 280,000 SF. -15 Million Dollar Project
13,000 SF. – 3 Million Dollar Project Constructed five complete tilt ups,
Ground up steel frame, concrete wainscoted interacted with 28 subcontractors and
structure in fully operational trolley yard. oversaw all site work.
Ghirardelli Chocolate III, IV & V Stanford Linear Accelerator
San Lenadro, CA Palo Alto, CA
35,200 SF. – 6 Million Dollar Project 10,000 SF. – 1 Million Dollar Project
High end remodel of two floors of office Constructed a ground up temporary
area; constructed a two story office structure power facility.
and retrofit loading docks while plant was
operational.
One Color Communications Atherton Middle School
Emeryville, CA Atherton, CA
30,000 SF. – 3.1 Million Dollar Project 15,000 SF. – 3 Million Dollar Project
Seismic retrofit and high end remodel of Ground up construction of library
fire damaged two-story brick building. and remodel of twenty classrooms
while classes in session.
Concord City Hall Antioch Junior High School
Concord, CA Antioch, CA
10,000 SF. – 2.5 Million Dollar Project 20,000 SF. – 3.1 Million Dollar Project
Seismic retrofit, rebuild and remodel fire Seismic retrofit and remodel Science &
Damaged Library and Building Dept. Humanitarian buildings while classes in
session.
Southwest Airlines Gate 26A Pacific Coast Container
Oakland Airport-Oakland, CA Oakland, CA
40,000 SF. – 3.2 Million Dollar Project 10,000 SF. – 1.5 Million Dollar Project
Constructed ground up passenger waiting Constructed an insulated drive-in freezer
area and airplane docking area at Terminal 2. with an underslab heat system.
Sacramento Senior Housing Lake MerrittBoathouse (HistoricRenovation)
Berkeley, CA Oakland, CA
7 Million Dollar Project. Constructed 12 Million Dollar Project. Installed coffer
Ground up 4 story wood frame complex dam and extensive micropile retrofit.
with a concrete podium deck. Incorporated new structural/architectural
elements.
NukeJobs is a nuclear jobs board that provides nuclear job seekers access to international directories of Nuclear Employers, Nuclear Resumes and Nuclear Jobs such as Nuclear Engineer Jobs, Nuclear Construction Jobs, Nuclear Power Plant Jobs, Nuclear Medicine Jobs, Nuclear Pharmacy Jobs, Nuclear Security Jobs, Nuclear Physics Jobs, Nuclear Reactor Jobs, Nuclear Material Jobs, Nuclear Safety Jobs, and Nuclear Waste Jobs.