Project Manager / Owner’s Representative for more than 25 years; experienced with steel construction, concrete block, big box tilt-up, reinforced pre-cast, class 1 clean-rooms, laboratories, food service, training and conference facilities. Knowledgeable in site infrastructure and services with proven abilities in the areas of managing people, budgets, schedules and CMP tracking. Excellent written, oral, and interpersonal skills.
On-site Project Manager for construction of 10 million dollar, 3 story block & pre-cast, 50,000 sq./ft., church facility. Project includes a 30’ high, 900 seat Worship Center with state-of-the-art audio-visuals, kitchen facilities, staff offices, meeting rooms, classrooms and juvenile facilities. My responsibilities include:
- Daily on-site inspection and approval of work performed.
- Addressd field construction problems and generated field sketches
- Responded to RFI's and approved change orders with relevance to schedule and budget.
- Final approval of architectural design changes and shop drawing submittals
- Represented Sarasota Baptist Church with County Plans Reviewers, Lakewood Ranch Commercial Architectural Review Committee and local utility companies
Pruett Builders, Inc., Sarasota, FL May 2002 - November 2006
Project Manager - Supervisor AutoCad Design Group
Headed up design group of leading edge luxury custom homebuilder. Design Group generated high quality working architectural construction drawings for permit from preliminary floor designs and conceptual elevations.
- Prioritized, scheduled and assigned design projects
- Initiated time saving CAD procedures to improve design cycle time
- Interfaced with County Plan Reviewers and clients as needed during design and construction phases of project.
- Responded to RFI’s from field Superintendents and resolved issues.
- Implemented design changes per feed-back from field Quality Control Inspector to continuously improve building methods.
Lucent Technologies, (Formerly AT&T) April 1984 - April 2002
Project Manager - Engineering Manager
Responsible for construction and design of all areas at the Orlando facility, including clean room manufacturing, maintenance, warehouses, manufacturing support, general office areas, conference, training and auditorium areas, medical, cafeteria food services and executive office suites.
- Designed, scheduled and managed construction projects
- Established project engineering teams.
- Directed construction contractors, generated project bid proposals and filed permit applications. Evaluated and compiled all associated documentation including schedules, progress and safety reports, meeting minutes, invoices and RFI’s.
- Solicited, interviewed, and hired engineers, designers and AutoCad users to meet the needs of Lucent Technologies specific business requirements.
- Contract Administrator of 3.5 million-dollar annually, engineering and design subcontractor contract, consisting 60 engineers and designers. Determined engineering and design schedules and optimum deployment of the contract personnel in Clean Room environment
- Tracked and negotiated plant wide space utilization. Facilitated the engineering, scheduling, and renovating of all new office relocations within the Lucent plant.
Willis & Paul Engineers, Denville, N.J March 1981 - April 1984
Designer – AutoCad Supervisor
Engineering design included architectural, mechanical, electrical, structural, material handling and P&ID diagrams for turn-key heavy-duty material handling conveyor systems.
- Managed AutoCad computer aided design system. Established engineering standards, protocols and documentation systems.
- Developed a complete set of custom AutoCad menus and Factory Standards for all engineering disciplines.
- Instructed full-time and casual AutoCad Users to implement new systems and protocols in order to reduced design and drafting hours.
Technical Skill Set
-AutoCad
-Primavera
-Expedition
-Microsoft Project
-Microsoft Word
-Microsoft Excel
-Microsoft Access
-Microsoft Power Point
-CNC Programming
-Core Draw
-Corel Paint
EDUCATION
-Bachelors of Science Degree in Management and Business, National-Louis University. Graduated with honors.
-Associates of Science Degree, Brevard Community College, Cocoa, Florida
-Brooklyn Technical High School, Academic and Industrial Design Diplomas, Brooklyn, New York
P r o j e c t L i s t
Most Recent First
Sarasota Baptist Church – Lakewood Ranch Campus
- 10 million dollar 50,000 sq/ft Worship Center Facility
- 8.6 million - Two Story Tilt-up, 120,000 sq./ft. building, housing corporate offices, state-of-the-art corporate training center, and executive conference center with catering and dining facilities.
- 4.5 million - Restaurant Style, Curtain Wall Cafeteria and Food Court combination seating 300.
- 2.6 million - Tilt-up concrete and glass Rotunda expansion Main Lobby Corporate Headquarters.
- 2.6 million - Auditorium seating 350 persons with state-of-the-art audio-visual
- 2.9 million – Corporate Plaza w/ fountains, pools, waterfalls & nature areas.
- 1.4 million Executive Lobby expansion – renovation
- 2.8 million – AT&T Stores in Orlando and Disney World (6 stores)
- 1.6 million – AT&T Space Ship Earth Attraction renovation – Disney World
- 200 million - Class 1 Cleanroom (60,000 sq/ft.)(Co PM)
- 12.4 million – Tilt-up, 2 Story office building (140,000 sq/ft)
- 6.4 million – Big Box Tilt-up warehouse 32’ high bay area (180,000 sq/ft)
- 7 million - Class 1 research laboratory cleanroom (20,000 sq/ft)
- 2.8 million – Bell Laboratories research facility (32,000 sq/ft.)
- 1.2 million - Conference Center (30,000 sq/ft.)
- 4.5 million - Office Center (120,000 sq/ft.)
- 1.6 million - Training Facility (state of the art 90,000 sq/ft)
- 2.3 million – Hazardous Gas Distribution and Storage Facility
- 1.2 million - Medical Facility (19,000 sq/ft.)
- .5 million – Parking Lot (1,000 cars) w/sewers, lights, curbs, & tr ee islands.
- .8 million – Fitness Center (6,000 sq/ft.)
- 1.7 million - State of the Art Auditorium
- Class 10 Cleanroom (50,000 sq/ft) w/waffle slab, shear walls, associated mechanical, air handling, and filtration equipment
- 15,000 KV Substations
- Cooling towers
- Power House (12,000 sq/ft.) – Chillers, generators, air dryers & boilers
- Water waste treatment facility (40,000 sq/ft.)
- Water polishing facility
- UPS Systems
- Microelectronics manufacturing facility (200,000 sq/ft.)
- Bell Laboratories (60,000 sq/ft.)
- Warehouse (65,000 sq/ft.)
- Offices (145,000 sq/ft.)
NukeJobs is a nuclear jobs board that provides nuclear job seekers access to international directories of Nuclear Employers, Nuclear Resumes and Nuclear Jobs such as Nuclear Engineer Jobs, Nuclear Construction Jobs, Nuclear Power Plant Jobs, Nuclear Medicine Jobs, Nuclear Pharmacy Jobs, Nuclear Security Jobs, Nuclear Physics Jobs, Nuclear Reactor Jobs, Nuclear Material Jobs, Nuclear Safety Jobs, and Nuclear Waste Jobs.