To work as part of a team in a stable construction firm that wants someone who will go the extra mile, who will not compromise safety or quality and still get the job done on time and under budget.
David Davies
EXPERIENCE
CCC Group - Bath, PA 06/29/2008 - 11/15/2009
Ironworker Foreman
Steel erection and upgrade of an existing concrete plant facility. To include preheater tower,
gas conditioning tower, clinker cooler, raw mill, blend/kiln feed, and various bag houses.
Erection of iron and duct work, conveyors and components. Track manpower hours and job
equipment as needed. Communicate with superintendents progress, RFI's and solutions with
engineering's approval.
Tradesman International - Brooksville, FL 02/01/2008 - 05/01/2008
Journeyman Ironwoker/Rigger
Steel erection and components in a concrete plant. Includes trusses, beams, columns, stair
stringers, handrail, and grating. Interpret structural blueprints.
Casey Industrial & US Trades Alexandria - Alexandria, IN 06/01/2007 - 10/31/2007
Master Ironworker/Foreman
Steel erection and placement of steel at an ethanol plant. Placement of machinery and
vessels.
Custom Industrial Services - North Augusta, SC 12/01/2006 - 05/31/2007
Journeyman Ironworker
Installation and fabrication of steel, siding, decking, grating, and handrails in the expansion of a
paper plant.
Ashmore Concrete - Augusta, GA 05/01/2006 - 10/31/2006
Project Superintendent
Projects included Fort Gordan NSA Communications Center, Hilton Hotel, and RBW Logistics
Corporation.
Responsible for setting up site, including layout of footings and walls. Schedule, monitor, and
ordering proper equipment (backhoes, dump trucks, rebar, forms, and concrete) and crew
sizing. Maintain budgets, process invoices, and control overhead costs. Supervised
Rodbusters, Form Carpenters, and Concrete Finishers.
Wabi America - Allendale, SC 10/01/2005 - 04/30/2006
Structural/Rigging Superintendent
Responsible for scheduling, monitoring, and inspecting all erection sequences of iron and
placement of machinery. Preplanning proper size cranes and rigging. Size of lifts ranged from
1000 lbs to 250,000 lbs. Maintain daily reports, log in received materials, document all RFIs
and change orders. Assign General Foreman and Foremen for specific projects for their crews.
Maintain safe working conditions, OSHA compliance mandatory, conduct daily safety meetings
and walk-throughs.
Suitt/BE&K Builders Group - North Augusta, SC 10/01/2003 - 10/31/2005
General Foreman
Projects included Bell and Evans/Farmers Pride Chicken Processing Plant, Gulf stream
Racetrack and Casino, USB Chemical Plant.
Reported to the General Superintendent. maintained safety and quality of work. Oversee
demolition, site preparedness, auger-castpiles, pilecaps and footers, proper concrete selection,
placement of forms, and precast. Some of my other duties included hiring qualified craftsmen
and promoting and or disciplinary actions. Documenting all field requests, materials,
equipment, RFI's, concrete QC and photographing work in progress.
EDUCATION
Stevens School of the Bible 09/01/1984 - 06/15/1986
Lenox, Massachusetts
Two years of College, full time Technical or Vocational School
Major: Youth Counseling
CERTIFICATIONS AND LICENSES
MSHA 10 issued by US Dept of Mining
OSHA 10 issued by US Dept of Labor
Construction safety and health.
NCCER issued by FLA State University
Industrial Ironworker Craft Certification and various safety courses.
REFERENCES: Available Upon Request
NukeJobs is a nuclear jobs board that provides nuclear job seekers access to international directories of Nuclear Employers, Nuclear Resumes and Nuclear Jobs such as Nuclear Engineer Jobs, Nuclear Construction Jobs, Nuclear Power Plant Jobs, Nuclear Medicine Jobs, Nuclear Pharmacy Jobs, Nuclear Security Jobs, Nuclear Physics Jobs, Nuclear Reactor Jobs, Nuclear Material Jobs, Nuclear Safety Jobs, and Nuclear Waste Jobs.